Route 9 and Route 83

  • Project: NJDOT Maintenance and Resurfacing Contract - 511
  • Owner: NJDOT
  • Engineer: NJDOT
  • Contract Amount: $226,676.00
  • Duration: 10 days
  • Description: Provided site clearing, saw cutting, milling, paving, landscaping and concrete as part of the realignment of the intersection at route 9 and route 83. The majority of the work was done at night.